NSEFI Representations |
|
Request for grant of interim relief to Renewable Power Developers projects on the Great Indian Bustard (GIB) matter pending before the Hon’ble Supreme Court.
MNRE is requested for extension in SCOD timelines by 8 months after the date of a final order of Hon’ble Supreme court against IA filed for modification and allow developers to commission the projects without attracting any LD for the delays due to GIB order which is beyond their controls.Read More
|
|
Request for grant of interim relief to Renewable Power Developers projects on the Great Indian Bustard (GIB) matter pending before the Hon’ble Supreme Court.
Request for interim relief & issue the advisory to all RE implementing agencies (SECI, NTPC, NHPC, state entities, DISCOM’s etc.) and grant the preliminary extension of 6 - 8 months in Scheduled commissioning date.Read More
|
|
Waiver of Inter-State Transmission losses on transmission of electricity generated from RE sources – for projects bid out upto 21st June 2021
Request to consider the cut-off date for applicability of ISTS losses as 21.06.2021 to protect the RE developers from such post-facto clarification, as non-applicability/non-waiver of ISTS losses.Read More
|
|
|
|
|
Top Stories |
|
Parliamentary panel for innovative tools like green banks, renewable finance obligation to boost clean energy
The Renewable Finance Obligation will make them invest a specific percentage of their investment in the renewable energy sector.Read More
|
|
REC third quarter profit up 23 per cent at Rs 2,773 crore
Total income rose to Rs 10,070.42 crore in the quarter from Rs 9,089.46 crore in the same period a year agoRead More
|
|
India targets domestic production with 40% PV import duty, boost to manufacturing-linked incentive
India's Union Budget, presented this week by Finance Minister Nirmala Sitharaman, allocates an extra INR 19,500 crore ($2.6 billion) to the production-linked incentive scheme for solar from April.Read More
|
|
S R Narasimhan takes additional charge as CMD POSOCO
He has over three decades' experience in power system operation spread across CEA, POWERGRID and POSOCO after an initial stint with BHELRead More
|
|
|